About the Overhead Rate Calculator
What is the Overhead Rate Calculator?
Indirect costs such as factory rent, supervision and power must be spread over the jobs or products that use them. The overhead absorption rate does this using a base such as labour hours, machine hours or labour cost.
Enter the budgeted overheads and the total of the base for the period to get the rate, then apply it to a job to find its full cost.
How to use the Overhead Rate Calculator
- Budgeted Overheads for the Period (₹) (sample: 12,00,000)
- Allocation Base (sample: Direct labour hours)
- Total of the Base for the Period (sample: 8,000)
- Base Used by This Job or Product (sample: 120)
- Direct Cost of This Job (₹) (sample: 45,000)
- Press Calculate Overhead Rate (results also refresh as you type). The result card shows the Overhead Absorption Rate, along with Overhead applied to this job, Total job cost and Overhead share of job cost.
Formula used
Overhead rate = Budgeted overheads ÷ Budgeted base
- Applied overhead = rate × base used by the job
- Job cost = direct cost + applied overhead
Use machine hours in automated plants and labour hours in labour-intensive work.
Worked example
These are the sample values already filled in the calculator above, and the result it returns for them:
| Input | Sample value |
|---|---|
| Budgeted Overheads for the Period (₹) | 12,00,000 |
| Allocation Base | Direct labour hours |
| Total of the Base for the Period | 8,000 |
| Base Used by This Job or Product | 120 |
| Direct Cost of This Job (₹) | 45,000 |
| Result | Value |
|---|---|
| Overhead Absorption Rate | ₹150 per hour |
| Overhead applied to this job | ₹18,000 |
| Total job cost | ₹63,000 |
| Overhead share of job cost | 28.6% |
Tips for using the Overhead Rate Calculator
- Compare applied and actual overheads at period end; the difference is under- or over-absorption.
- Use separate rates for departments with very different cost structures.